Does anyone have any info on Shoshone comming back online? I heard they were going to be done working on it in September and will be calling for more water soon.
 

·
Registered
Joined
·
22 Posts
Discussion Starter #4
here is a quote from a post on this forum "Currently, the Shoshone Hydro Plant is operating at about half capacity, which requires about 700 cfs of water. Xcel Energy is unable to run Shoshone at full capacity while it works on repairs to the tunnel that runs about two miles from the Hanging Lakes power plant dam to the power plant itself. The work could last until early September.

A call on the river, such as the Shoshone 1,250 cfs water right, forces junior water rights holders to replace diverted water from reservoir storage or to stop diverting, thus boosting flows as they decline with the natural drop of the runoff throughout the summer.
"

Sounds like river will be back up to at least 1250 cfs soon!!!!!
 